Week of June 26, 2017

  • Notice to Proceed (NTP) was issued to Water Rock Construction on June 14, 2017.  NTP allows the contractor to begin work on the project.
  • Public access to Moorhen Marsh was closed on June 14, 2017 in order to allow the contractor to begin working in the marsh.
  • Once the NTP was issued, the contractor began mobilizing the necessary equipment and materials to begin construction work.
  • Construction activity began on the site on June 20, 2017.
  • The contractor is currently completing the de-watering process in ponds D and E.