Following is a summary of main work items during the week July 17, 2017:

•Completed vegetation removal and drying in Ponds C, D and
E (except small area by tree with nest, pond C).
•Continued ripping and drying the soils in ponds C, D and E.
•Continued dewatering local ponding water in Pond E.
•Wallace-Kuhl (field geotechnical) took in-situ density tests on pond material.