Construction Updates- Week of March 19, 2018

The majority of Phase A construction is finished. Below are highlights of construction activities completed in February and early March:

  • Completed terrestrial plantings (except for dip netting area)
  • Installed irrigation system
  • Installed the retaining wall in the dip net area in Pond E
  • Hydro-seeded levee trails

The remaining tasks to complete Phase A are listed below and MVSD expects all work to be completed by April 6th:

  • Install decomposed granite between the vehicle bridge and dip netting area
  • Install landscape boulders and picnic bench at dip netting area
  • Install terrestrial plants around dip netting area
  • Install emergent vegetation in Ponds C, D, and E
  • Install canal gates
  • Fill Ponds C, D, and E