The majority of Phase A construction is finished. Below are highlights of construction activities completed in February and early March:
- Completed terrestrial plantings (except for dip netting area)
- Installed irrigation system
- Installed the retaining wall in the dip net area in Pond E
- Hydro-seeded levee trails
The remaining tasks to complete Phase A are listed below and MVSD expects all work to be completed by April 6th:
- Install decomposed granite between the vehicle bridge and dip netting area
- Install landscape boulders and picnic bench at dip netting area
- Install terrestrial plants around dip netting area
- Install emergent vegetation in Ponds C, D, and E
- Install canal gates
- Fill Ponds C, D, and E