Moorhen Marsh Phase B- Construction Week of August 20, 2018
Recent work performed:
- Completed levee reconstruction with geogrid in pond A-2 and A-1.
- Constructed 3 islands in pond A-2 and began island construction in pond A-1
- Formed and poured concrete for the boardwalk and viewing platform abutments in pond A-2.
- Installed timber piles for the boardwalk and viewing platform abutments in pond A-2.
- Installed 2 water control structures.
- Began dredging in Peyton Slough.
- Excavated and installed levee keyways in Fat Slough and began levee reconstruction with geogrid.
- Began excavating and installing levee keyways in pond B and began levee reconstruction with geogrid on the west side along Peyton Slough.
- Continued drying and moisture conditioning pond B soils.
Upcoming work:
- Complete levee reconstruction and island construction in pond A-1.
- Complete levee reconstruction in Fat Slough.
- Continue keyway installation and levee reconstruction in pond B.
- Complete dredging in Peyton Slough.
- Install the 3 remaining water control structures.
- Begin installation of the outlet structures to Peyton Slough.
- Begin installation of rip rap in ponds A-2 and A-1.
- CCC scheduled for mid September to start constructing the boardwalk and viewing platform.